Forum Discussion
Did GTM+LTM need to remove from sync group before Upgrade HF?
Hi
I've plan to upgrade HF GTM+LTM (provision 2 module) from 11.4.1 HF3 to 11.4.1 HF9
I've 4 GTM+LTM (First pair at site one , another two at site two), It's all in GTM sync group .
Did I need to remove GTM from sync group in site one before upgrade?
Or can I Just upgrade both GTM in site one ... and then Upgrade GTM in site two respectively ?
Thank you very much
- kridsanaCirrocumulus
Hi Hannes
Can I use this plan?
In Main site have 2 F5 with redundant pair (Active-standby) 1. Upgrade Standby unit (Unit 2) 2. reboot standby unit to newly upgrade 3. failover 4. Perform upgrade on Unit not yet upgraded (Perform step 1-2 on Unit 1)
Then I've to wait for another day to perform upgrade at Another site (Another DC) with 2 F5. And perform the same step I've done with Main site.
Is this plan work?
Thank you very much
- Hannes_RappNimbostratus
No need to do that. During the upgrade, make sure you have 1 appliance active/operational at a time, put the other 3 in "Forced Offline" state.
I'd recommend the following procedure:
1) Sync configurations in all sites
Recent Discussions
Related Content
* Getting Started on DevCentral
* Community Guidelines
* Community Terms of Use / EULA
* Community Ranking Explained
* Community Resources
* Contact the DevCentral Team
* Update MFA on account.f5.com