Mar 27, 2026 - For details about updated CVE-2025-53521 (BIG-IP APM vulnerability), refer to K000156741.

Forum Discussion

Re: Unable to migrate using F5 journeys

Jeffrey, thank you for your input.

I successfully managed the migration using journeys by following these steps:

  1. Migrated from the existing UCS (v12) to the r2600 tenant (v15).
  2. Then migrated from the r2600 tenant (v15) to the r2600 tenant (v17).

Initially, I was attempting the following procedure:

  1. Migrated from the existing UCS (v12) to a UCS (v15).
  2. Then from UCS (v15) to r2600 tenant (v17).

I realize now that the mistake in my initial approach was trying to migrate in two steps while the UCS content remained at v12. Your advice was a great help!

No RepliesBe the first to reply