Hi - we have 2 APM's in a cluster on one ISP link, and we want to migrate to a new network on another ISP link in a new datacentre.
We wish to do this with as little downtime / outage as possible, and wanted to know the basic steps to do this.
- RaghavendraSY_7
Cumulonimbus
Can you please let me know whether you are going to use seperate APM module F5 devices on new datancenter or You are going to use same F5 evices on another datancenter.
Steps to migrate existing APM F5 devices to different set of APM modules on another datancetner.
- Configure Management IP for new APM F5 devices
- Export UCS file from the existing APM F5 devices
- Import to new F5 APM devices
- Install UCS file on new F5 devices by enabling only management interfce (disable all other interfaces)
- Now during the maintenance window enable interfaces on new F5 APM devices and disable interfaces on old F5 devices.
- Once done please test your applications.
Hope this helps.
- JamesC1
Altostratus
Hi - I will be migrating the existing Big-IP hardware devices to the new datacenter. The business has enough appetite for risk to be able to run on a single node for a period of time, or we may be able to get a loan device to facilitate this if it is going to be easier.
- RaghavendraSY_7
Cumulonimbus
Then above steps will sufficient for the migration activity (with minimum downtime).
- RaghavendraSY
Altostratus
Can you please let me know whether you are going to use seperate APM module F5 devices on new datancenter or You are going to use same F5 evices on another datancenter.
Steps to migrate existing APM F5 devices to different set of APM modules on another datancetner.
- Configure Management IP for new APM F5 devices
- Export UCS file from the existing APM F5 devices
- Import to new F5 APM devices
- Install UCS file on new F5 devices by enabling only management interfce (disable all other interfaces)
- Now during the maintenance window enable interfaces on new F5 APM devices and disable interfaces on old F5 devices.
- Once done please test your applications.
Hope this helps.
- JamesC1
Altostratus
Hi - I will be migrating the existing Big-IP hardware devices to the new datacenter. The business has enough appetite for risk to be able to run on a single node for a period of time, or we may be able to get a loan device to facilitate this if it is going to be easier.
- RaghavendraSY
Altostratus
Then above steps will sufficient for the migration activity (with minimum downtime).
Recent Discussions
Related Content
* Getting Started on DevCentral
* Community Guidelines
* Community Terms of Use / EULA
* Community Ranking Explained
* Community Resources
* Contact the DevCentral Team
* Update MFA on account.f5.com