Forum Discussion
Muhammad_57196
Nimbostratus
Jun 17, 2009Active Active Datacenter design
We are going through design phase of the our project that involves the following:
1. Two datacenters (apart 15 km) running active/active.
2. We have layer 2 connectivity at each ...
The_Bhattman
Nimbostratus
Nov 13, 2009Since both pairs basically have different IP addresses between DR and active pairs so we cannot 100% guarantee they are perfectly synchronized. Our only method for now is tightly controlled deployment and maintenance strategy. For example we add new vips and pools in the Active and DR environments and then follow up with a montly audit to ensure process and procedure is followed.