About F5 VE License Question

Hello ,

I have a VE version of License.
This is the information about License

#-------------------------------------------------------------------
  F5 Product            : F5-BIG-APMVE200MV16 BIG-IP VIRTUAL EDITION: APM BASE LICENSE (200M,100
  Usage                 : Production
  Product Order Status  : Sales
  License Time Limit    : N/A
#-------------------------------------------------------------------
# Service and Warranty Information
#-------------------------------------------------------------------
  Entitled Service      : 02-06-2018 - 02-15-2025 (F5-SVC-BIG-VE+STDL3)
  Warranty End Date     : 12-21-2018
#-------------------------------------------------------------------

I would like to ask what will happen after 02-15-2025.
1. will the APM service stop?
2. will I be able to open a case?

Thanks

1 Reply

    1. This is a perpetual license. Time-limited licenses have a License Time Limit date.
    2. You've purchased support (to open cases) through 2-15-2025.