- Oct 29, 2018
The answer to my initial question - yes, it is possible to configure DSC with VE v13, at least, using LAB license. But this requires 8 GB of RAM and 4 CPUs per VE. Not sure if this can be performed with Trial or Evaluation licenses as I have no possibility to test this.
The answer to my initial question - yes, it is possible to configure DSC with VE v13, at least, using LAB license. But this requires 8 GB of RAM and 4 CPUs per VE. Not sure if this can be performed with Trial or Evaluation licenses as I have no possibility to test this.
Hi Philip
I have moved from VMware Fusion to ESXi environment (from laptop to external LAB environment). ESXi environment gave an opportunity to allocate more resources to each VM. I agree this might be an issue with the Evaluation license. As far as I know the Trial is for 90 days. And evaluation is for 30 days. Could you tell what is the license for 45 days?
Thank you!
Recent Discussions
Related Content
* Getting Started on DevCentral
* Community Guidelines
* Community Terms of Use / EULA
* Community Ranking Explained
* Community Resources
* Contact the DevCentral Team
* Update MFA on account.f5.com